Sealed Pavement Rehabilitation - Kergunyah Road

Share Sealed Pavement Rehabilitation - Kergunyah Road on Facebook Share Sealed Pavement Rehabilitation - Kergunyah Road on Twitter Share Sealed Pavement Rehabilitation - Kergunyah Road on Linkedin Email Sealed Pavement Rehabilitation - Kergunyah Road link

About this project

Each year, we undertake a number of sealed road maintenance and improvement programs, including:

Our Sealed Pavement Rehabilitation program targets roads that have numerous failures and significant roughness and require full-width reconstructions.

Roads identified for this level of works have generally reached a condition where our other sealed road renewal programs are not sufficient to bring the road back to an acceptable standard.

Why is this project being undertaken?

The ‘pavement’ of a sealed road refers to the various layers of crushed rock, gravels and natural material which exist under the black sealed surface. This sandwich of compacted materials provides the structural base of the road that supports the traffic while the thin bitumen surface acts as the waterproofing layer to prevent the pavement from getting excessively wet and falling apart.

Over a road's life, traffic slowly breaks down the pavement materials until they can no longer support the traffic loads, which causes them to deform and ultimately fail.

What is happening and when?

A large proportion of this years’ budget will fund the rehabilitation of approximately 1.1km of Kergunyah Road, made up from five different segments of varying length along its 3km stretch. The scope involves a variety of rehabilitation treatments including, in-situ cement and lime stabilisation, recycling or replacement of existing gravel pavements, new gravel overlays, seal reinstatement and some associated drainage clearing works.

This road has been subject to numerous pavement failures and has been ‘patched’ over many years using a combination of asphalt and stabilising treatments. The sections of road in the scope of these works continue to fail which has prompted this larger scale rehabilitation treatment proposal rather than more patching.

These larger scale works are typically scheduled to occur in the warmer drier spring/summer months when weather conditions are more suitable for road construction activities.

The tender for these works was awarded by Council at its September 2024 meeting.

What will be the impact of these works?

These works will be a significant upgrade of the road and will greatly improve driving conditions for the community.

While the works are underway, intermittent road closures are likely to be required at different stages to allow for the works to be completed efficiently and safely. We will provide updates during construction should any closures be prolonged.

About this project

Each year, we undertake a number of sealed road maintenance and improvement programs, including:

Our Sealed Pavement Rehabilitation program targets roads that have numerous failures and significant roughness and require full-width reconstructions.

Roads identified for this level of works have generally reached a condition where our other sealed road renewal programs are not sufficient to bring the road back to an acceptable standard.

Why is this project being undertaken?

The ‘pavement’ of a sealed road refers to the various layers of crushed rock, gravels and natural material which exist under the black sealed surface. This sandwich of compacted materials provides the structural base of the road that supports the traffic while the thin bitumen surface acts as the waterproofing layer to prevent the pavement from getting excessively wet and falling apart.

Over a road's life, traffic slowly breaks down the pavement materials until they can no longer support the traffic loads, which causes them to deform and ultimately fail.

What is happening and when?

A large proportion of this years’ budget will fund the rehabilitation of approximately 1.1km of Kergunyah Road, made up from five different segments of varying length along its 3km stretch. The scope involves a variety of rehabilitation treatments including, in-situ cement and lime stabilisation, recycling or replacement of existing gravel pavements, new gravel overlays, seal reinstatement and some associated drainage clearing works.

This road has been subject to numerous pavement failures and has been ‘patched’ over many years using a combination of asphalt and stabilising treatments. The sections of road in the scope of these works continue to fail which has prompted this larger scale rehabilitation treatment proposal rather than more patching.

These larger scale works are typically scheduled to occur in the warmer drier spring/summer months when weather conditions are more suitable for road construction activities.

The tender for these works was awarded by Council at its September 2024 meeting.

What will be the impact of these works?

These works will be a significant upgrade of the road and will greatly improve driving conditions for the community.

While the works are underway, intermittent road closures are likely to be required at different stages to allow for the works to be completed efficiently and safely. We will provide updates during construction should any closures be prolonged.

  • Friday 1 November update

    Share Friday 1 November update on Facebook Share Friday 1 November update on Twitter Share Friday 1 November update on Linkedin Email Friday 1 November update link

    We've completed this rehabilitation project and more than 1.1km of Kergunyah Road has now been upgraded.
    Road sealing work in rural valley

  • Friday 18 October update

    Share Friday 18 October update on Facebook Share Friday 18 October update on Twitter Share Friday 18 October update on Linkedin Email Friday 18 October update link

    We’ve made great progress on works this week, despite the wet weather today.

    Works will continue for the next one to two weeks.

    Please take extra care when driving through the work sites until the new surface is finished and be aware that you may encounter minor delays.

    Road works in rural valley

  • Friday 11 October update

    Share Friday 11 October update on Facebook Share Friday 11 October update on Twitter Share Friday 11 October update on Linkedin Email Friday 11 October update link

    Works will commence next week (weather permitting).

    While the road will remain open for the duration of the works, please be aware that short delays will be likely.

    Works are scheduled to be completed in two-to-three weeks.

    Rural sealed road surrounded by paddocks

Page last updated: 30 Oct 2024, 07:55 PM