Baarmutha Park Sports Nets

Share Baarmutha Park Sports Nets on Facebook Share Baarmutha Park Sports Nets on Twitter Share Baarmutha Park Sports Nets on Linkedin Email Baarmutha Park Sports Nets link

About this project

We're upgrading the cricket practice lanes at Beechworth's Baarmutha Park to an all-purpose sporting facility.

Why is this project being undertaken?

This project will see us replace the ageing and non-compliant three lane practice nets with a four lane fully enclosed facility that has been designed to Cricket Australia Community Cricket Facility Guidelines.

The upgrade will enable greater participation for all members of the community in a safer and more enjoyable environment.

What is happening and when?

This project is nearing completion with the cricket facility fully constructed. Remaining works includes installation of new fire hydrant.

How is it being funded?

This project is being funded through Sport and Recreation Victoria’s 2022 Community Cricket Program.

Funding ContributorAmount
Beechworth Wanderers Cricket Club$40,000
Cricket Australia$30,000
Sport and Recreation Victoria$100,000
Indigo Shire Council$225,000 + $57,000
Additional funding for roof
Beechworth and District Community Bank$150,000
TOTAL$602,000


About this project

We're upgrading the cricket practice lanes at Beechworth's Baarmutha Park to an all-purpose sporting facility.

Why is this project being undertaken?

This project will see us replace the ageing and non-compliant three lane practice nets with a four lane fully enclosed facility that has been designed to Cricket Australia Community Cricket Facility Guidelines.

The upgrade will enable greater participation for all members of the community in a safer and more enjoyable environment.

What is happening and when?

This project is nearing completion with the cricket facility fully constructed. Remaining works includes installation of new fire hydrant.

How is it being funded?

This project is being funded through Sport and Recreation Victoria’s 2022 Community Cricket Program.

Funding ContributorAmount
Beechworth Wanderers Cricket Club$40,000
Cricket Australia$30,000
Sport and Recreation Victoria$100,000
Indigo Shire Council$225,000 + $57,000
Additional funding for roof
Beechworth and District Community Bank$150,000
TOTAL$602,000


  • Update - December 2025

    Share Update - December 2025 on Facebook Share Update - December 2025 on Twitter Share Update - December 2025 on Linkedin Email Update - December 2025 link

    Excitement is building for the Beechworth Wanderers Cricket Club and the wider community, with the new cricket facility at Baarmutha now in its final stages.

    The installation of the soft netting has been completed, marking a major milestone in the project. A few minor finishing touches are scheduled for later this week, after which a compliance walk through with the contractor will take place.

    With these final steps underway, the facility is on track to open shortly, ready to welcome the Wanderers and the community to enjoy cricket in a modern, purpose built space.

    Excitement is building for the Beechworth Wanderers Cricket Club and the wider community, with the new cricket facility at Baarmutha now in its final stages.

    The installation of the soft netting has been completed, marking a major milestone in the project. A few minor finishing touches are scheduled for later this week, after which a compliance walk through with the contractor will take place.

    With these final steps underway, the facility is on track to open shortly, ready to welcome the Wanderers and the community to enjoy cricket in a modern, purpose built space.

  • Update - October 2025

    Share Update - October 2025 on Facebook Share Update - October 2025 on Twitter Share Update - October 2025 on Linkedin Email Update - October 2025 link

    Construction is progressing swiftly, with the concrete floor slab and footpath now complete and roof installation finished. Indoor lighting and electrical works are scheduled to commence in the coming weeks.

    Construction is progressing swiftly, with the concrete floor slab and footpath now complete and roof installation finished. Indoor lighting and electrical works are scheduled to commence in the coming weeks.

  • Update - September 2025

    Share Update - September 2025 on Facebook Share Update - September 2025 on Twitter Share Update - September 2025 on Linkedin Email Update - September 2025 link

    Significant progress has been made, with the structural framework and wall cladding now complete.

    Significant progress has been made, with the structural framework and wall cladding now complete.