Share Urban Road Sealing Program on FacebookShare Urban Road Sealing Program on TwitterShare Urban Road Sealing Program on LinkedinEmail Urban Road Sealing Program link
About this project
We're upgrading a number of roads across the Shire to improve road conditions, reduce dust hazards and maintenance for Council. This program also includes our Kerb Renewal project, which enhances roadside parking.
Why is this project being undertaken?
We're undertaking this program to improve the road surface and amenity as part of our ongoing commitment to improving liveability and connection in our communities.
How is it being funded?
These works are being funded through our Capital Works budget.
Funding Contributor
Amount
Indigo Shire Council
$259,500
TOTAL:
$259,500
Roads included in the current program
Road
Locality
Road length (m)
Barkly Street
Beechworth
280
Buckland Gap Road Service Road
Beechworth
315
Taylor Street
Beechworth
140
Wood Street
Beechworth
70
Gordon Street
Chiltern
110
McLean Street
Chiltern
340
Mackay Street (flood damage)
Chiltern
10
Nott Street - road shoulder
Rutherglen
126
Booth Street - road shoulder
Rutherglen
115
Twist Creek Road
Yackandandah
200
What is happening and when?
The major construction works for this project were completed in May 2024, with the remainder of works carried out over the following months up to October 2024.
About this project
We're upgrading a number of roads across the Shire to improve road conditions, reduce dust hazards and maintenance for Council. This program also includes our Kerb Renewal project, which enhances roadside parking.
Why is this project being undertaken?
We're undertaking this program to improve the road surface and amenity as part of our ongoing commitment to improving liveability and connection in our communities.
How is it being funded?
These works are being funded through our Capital Works budget.
Funding Contributor
Amount
Indigo Shire Council
$259,500
TOTAL:
$259,500
Roads included in the current program
Road
Locality
Road length (m)
Barkly Street
Beechworth
280
Buckland Gap Road Service Road
Beechworth
315
Taylor Street
Beechworth
140
Wood Street
Beechworth
70
Gordon Street
Chiltern
110
McLean Street
Chiltern
340
Mackay Street (flood damage)
Chiltern
10
Nott Street - road shoulder
Rutherglen
126
Booth Street - road shoulder
Rutherglen
115
Twist Creek Road
Yackandandah
200
What is happening and when?
The major construction works for this project were completed in May 2024, with the remainder of works carried out over the following months up to October 2024.
Share Wednesday 29 May update on FacebookShare Wednesday 29 May update on TwitterShare Wednesday 29 May update on LinkedinEmail Wednesday 29 May update link
Major works have been completed across the Shire, with our crews putting the finishing touches on Taylor Street and Barkly Street this week.
Page last updated: 30 Oct 2024, 07:53 PM
Lifecycle
Major works
Urban Road Sealing Program has finished this stage
Minor works and touch-ups
Urban Road Sealing Program has finished this stage
Complete
Urban Road Sealing Program is currently at this stage