Share Boorhaman East Road Bridge Renewal on FacebookShare Boorhaman East Road Bridge Renewal on TwitterShare Boorhaman East Road Bridge Renewal on LinkedinEmail Boorhaman East Road Bridge Renewal link
About this project
The upgrade of the concrete bridge over Diddah Diddah Creek on Boorhaman East Road, was completed in June 2025.
Why was this project being undertaken?
Structural investigations, carried out as part of our bridge asset management program, have identified long-term load capacity issues with the bridge beams and culverts that carry traffic on Boorhaman East Road.
To accommodate current and future traffic loads within acceptable safety factors, options to strengthen the bridge and upgrade the culverts were explored in detail but ultimately an option to fully replace both with a completely new bridge proved to be a more economical, lower risk pathway, with improved outcomes for the waterway area.
If these works were not to occur, the bridge load limit would need to be significantly reduced in the long term, which we don't consider a viable option for this important agricultural link road.
How was it being funded?
This project is jointly funded by the Federal Government's Bridges Renewal Program and Council's Capital Work bridge renewal fund.
Funding Contributor
Amount
Australian Government – Bridges Renewal Program Grant
$559,708
Indigo Shire Council
$139,928
TOTAL
$699,636
About this project
The upgrade of the concrete bridge over Diddah Diddah Creek on Boorhaman East Road, was completed in June 2025.
Why was this project being undertaken?
Structural investigations, carried out as part of our bridge asset management program, have identified long-term load capacity issues with the bridge beams and culverts that carry traffic on Boorhaman East Road.
To accommodate current and future traffic loads within acceptable safety factors, options to strengthen the bridge and upgrade the culverts were explored in detail but ultimately an option to fully replace both with a completely new bridge proved to be a more economical, lower risk pathway, with improved outcomes for the waterway area.
If these works were not to occur, the bridge load limit would need to be significantly reduced in the long term, which we don't consider a viable option for this important agricultural link road.
How was it being funded?
This project is jointly funded by the Federal Government's Bridges Renewal Program and Council's Capital Work bridge renewal fund.
Funding Contributor
Amount
Australian Government – Bridges Renewal Program Grant
Share Friday 20 June update on FacebookShare Friday 20 June update on TwitterShare Friday 20 June update on LinkedinEmail Friday 20 June update link
Boorhaman East Road Bridge open
We’re pleased to share that the upgraded Boorhaman East Road bridge over Diddah-Diddah Creek has officially reopened to traffic following the completion of barrier works earlier this week.
Motorists are reminded to observe the reduced speed limits still in place while the new road surface settles and contractors work to safely remove the temporary side road and bridge.
Thank you to all road users and local residents for your patience and understanding during the delivery of this important infrastructure upgrade.
Boorhaman East Road Bridge open
We’re pleased to share that the upgraded Boorhaman East Road bridge over Diddah-Diddah Creek has officially reopened to traffic following the completion of barrier works earlier this week.
Motorists are reminded to observe the reduced speed limits still in place while the new road surface settles and contractors work to safely remove the temporary side road and bridge.
Thank you to all road users and local residents for your patience and understanding during the delivery of this important infrastructure upgrade.
Share Friday 28 March update on FacebookShare Friday 28 March update on TwitterShare Friday 28 March update on LinkedinEmail Friday 28 March update link
Further construction progress was made this week with the main supporting beams now in place.
Construction of the deck is also well advanced, in preparation for a concrete pour later next week.
Further construction progress was made this week with the main supporting beams now in place.
Construction of the deck is also well advanced, in preparation for a concrete pour later next week.
Share Friday 21 March update on FacebookShare Friday 21 March update on TwitterShare Friday 21 March update on LinkedinEmail Friday 21 March update link
The welcome rain this week didn’t slow construction progress, with installation and testing of the pile supports now complete, and assembly of the steel structure progressing well.
Works to finish shaping and rock armouring the new wider waterway will be completed next before placement of the main bridge beams.
The temporary side road and associated speed limits remain in place, and we ask that road users take care in the changed conditions.
The welcome rain this week didn’t slow construction progress, with installation and testing of the pile supports now complete, and assembly of the steel structure progressing well.
Works to finish shaping and rock armouring the new wider waterway will be completed next before placement of the main bridge beams.
The temporary side road and associated speed limits remain in place, and we ask that road users take care in the changed conditions.
Share Friday 14 March update on FacebookShare Friday 14 March update on TwitterShare Friday 14 March update on LinkedinEmail Friday 14 March update link
Works continued this week with the temporary bridge now open, and demolition of the existing bridge well advanced.
Installation of the deep steel piles to support the new longer span bridge is also underway.
Please be aware that reduced speed limits are in effect around the worksite and on the temporary bridge.
Weather permitting, construction is expected to take approximately six to eight weeks.
Works continued this week with the temporary bridge now open, and demolition of the existing bridge well advanced.
Installation of the deep steel piles to support the new longer span bridge is also underway.
Please be aware that reduced speed limits are in effect around the worksite and on the temporary bridge.
Weather permitting, construction is expected to take approximately six to eight weeks.
Share Friday 7 March Update on FacebookShare Friday 7 March Update on TwitterShare Friday 7 March Update on LinkedinEmail Friday 7 March Update link
Works on the Boorhaman East Road Bridge upgrade project began this week, with installation of the temporary side road and bridge well advanced.
Our local contractor, Murray Valley Piling is aiming to complete installation over the weekend and once in place, the temporary structure will carry road traffic to enable the removal of the existing bridge and culverts, before construction of the new longer span bridge commences.
Please be aware that reduced speed limits are in effect around the worksite and on the temporary bridge.
Weather permitting, construction is expected to take approximately six to eight weeks.
Works on the Boorhaman East Road Bridge upgrade project began this week, with installation of the temporary side road and bridge well advanced.
Our local contractor, Murray Valley Piling is aiming to complete installation over the weekend and once in place, the temporary structure will carry road traffic to enable the removal of the existing bridge and culverts, before construction of the new longer span bridge commences.
Please be aware that reduced speed limits are in effect around the worksite and on the temporary bridge.
Weather permitting, construction is expected to take approximately six to eight weeks.
Page last updated: 22 Aug 2025, 03:24 PM
Lifecycle
Feasibility
Boorhaman East Road Bridge Renewal has finished this stage
Detailed design
Boorhaman East Road Bridge Renewal has finished this stage
June/July 2024
Tender awarded
Boorhaman East Road Bridge Renewal has finished this stage
September 2024
Construction
Boorhaman East Road Bridge Renewal has finished this stage
Complete
Boorhaman East Road Bridge Renewal is currently at this stage