About this project
Council has over 469 kilometres of sealed roads to maintain and funds an annual renewal program to resurface a small proportion of this urban and rural network.
This program is predominately developed by reviewing the condition and age of sections of road, but also for improved amenity within the streetscape.
Why is this project being undertaken?
As a road surface ages, the bitumen within it becomes brittle and can crack or lose its ability to hold onto the stone aggregate surface. This leads to water penetrating the underlying structure of the road which can cause more major failures like potholes.
So while your road or street might look to be in serviceable condition, by the time of resurfacing it is likely reaching this point of brittleness and may soon begin to fail. Most sealed roads are resurfaced once every 15-25 years, varying according to a wide variety of factors.
What is happening and when?
Council has approved the award of the contract for its 2026/27 Annual Resealing program to LFT Bitumen Pty Ltd based in Albury/Wodonga. The $696,184 contract will see sections of the following roads resurfaced.
Works are proposed to be completed, weather permitting, over a two-week period in early November. You may notice minor works on these roads, by our Road Maintenance staff, in the lead up to help prepare the road. Please feel free to review our FAQ’s on this page for more information around what to expect, before, during and after.
Road or Street Name
Element
Start Reference
Start Chainage (m)
End Reference
End Chainage (m)
Overall Segment length (m)
Location
Up River Rd
Full width
00 @ Gooramadda Rd 7375 start @ Granthams Rd
7,375
Federation Way DTP Road reserve boundary and seal change
11,667
4,292
Gooramadda
Campbell St
Full width
00 @ Culbertson St 96m at seal and width change
96
Gooramadda Rd
1,341
1,245
Rutherglen
Audley St
Full width
High St
0
Howlong Rd (MV Hwy)
387
387
Rutherglen
Hopetoun Rd
Full width
Howlong St (MV Hwy)
0
Seal change
70
70
Rutherglen
Myrtleford-Stanley Rd
Full width
00 @ Little Scotland Rd Start @ seal change as marked
3,066
Seal change
6,076
3,010
Stanley
Bells Flat Rd
Full width
Yackandandah_Wodonga Rd
0
Marks on road just past McIntosh Lane
950
950
Yackandandah
Mahon Lane
Full width
00 @ Santoriam Rd Start @ new seal
2,535
Racecourse Rd
3,095
560
Yackandandah
Kiewa-Bonegilla Rd
Full width
00 @ Kiewa East Rd
4
Width change (end of kerb section)
462
458
Tangambalanga
Forge Crt
Full width
Kiewa-Bonegilla Rd
0
End road reserve
80
68
Tangambalanga
Sandy Creek Rd
Full width
00 @ Lockhart's Gap Rd
0
As marked
90
90
Sandy Creek
Havelock Rd
Full width
Balaclava Rd / End High St
0
Seal change
451
451
Beechworth
Alma Rd
Full width
Havelock Rd
0
Seal change
537
537
Beechworth
Polmear Ln
Full width
Buckland Gap Rd
0
End seal past bend
190
190
Beechworth
Moffat Rd
Full width
00 @ end of Barkly Start of new seal
310
Skerry St
540
230
Chiltern
Alliance St
Full width
Main St (Beechworth-Chiltern Rd)
0
Seal change
111
111
Chiltern
Alliance St C/P (at Tourist Park)
Car parking & bus stop
Alliance St
0
Alliance St
80
80
Chiltern
About this project
Council has over 469 kilometres of sealed roads to maintain and funds an annual renewal program to resurface a small proportion of this urban and rural network.
This program is predominately developed by reviewing the condition and age of sections of road, but also for improved amenity within the streetscape.
Why is this project being undertaken?
As a road surface ages, the bitumen within it becomes brittle and can crack or lose its ability to hold onto the stone aggregate surface. This leads to water penetrating the underlying structure of the road which can cause more major failures like potholes.
So while your road or street might look to be in serviceable condition, by the time of resurfacing it is likely reaching this point of brittleness and may soon begin to fail. Most sealed roads are resurfaced once every 15-25 years, varying according to a wide variety of factors.
What is happening and when?
Council has approved the award of the contract for its 2026/27 Annual Resealing program to LFT Bitumen Pty Ltd based in Albury/Wodonga. The $696,184 contract will see sections of the following roads resurfaced.
Works are proposed to be completed, weather permitting, over a two-week period in early November. You may notice minor works on these roads, by our Road Maintenance staff, in the lead up to help prepare the road. Please feel free to review our FAQ’s on this page for more information around what to expect, before, during and after.
Road or Street Name
Element
Start Reference
Start Chainage (m)
End Reference
End Chainage (m)
Overall Segment length (m)
Location
Up River Rd
Full width
00 @ Gooramadda Rd 7375 start @ Granthams Rd
7,375
Federation Way DTP Road reserve boundary and seal change
11,667
4,292
Gooramadda
Campbell St
Full width
00 @ Culbertson St 96m at seal and width change
96
Gooramadda Rd
1,341
1,245
Rutherglen
Audley St
Full width
High St
0
Howlong Rd (MV Hwy)
387
387
Rutherglen
Hopetoun Rd
Full width
Howlong St (MV Hwy)
0
Seal change
70
70
Rutherglen
Myrtleford-Stanley Rd
Full width
00 @ Little Scotland Rd Start @ seal change as marked