Annual Gravel Road Resheeting program 2024/25

Share Annual Gravel Road Resheeting program 2024/25 on Facebook Share Annual Gravel Road Resheeting program 2024/25 on Twitter Share Annual Gravel Road Resheeting program 2024/25 on Linkedin Email Annual Gravel Road Resheeting program 2024/25 link

About this project

We're commencing our annual program to resheet a proportion of the unsealed gravel roads across the Shire.

Why is this project being undertaken?

We routinely maintain around 1000km of unsealed gravel roads across the Shire. The 2024/25 program will see works completed on a number of roads in the east and west of the Shire, totalling approximately 20km. The roads will be graded, roadside drains will be improved, and new gravel material will be laid and compacted to improve driving conditions.

How is it being funded?

These works are funded through our Capital Works Program.

Funding Contributor
Amount
Indigo Shire Council
$680,000
TOTAL:
$680,000


Roads included in the current program

WEST




Road

Locality

Chainage Starts at

Length (m)

Cofield Lane

Wahgunyah

St Leonards Rd

400

Boundary Rd

Norong

West of Fed Way

2300

Melvilles Rd

Cornishtown

Great Northern

3400

Watch Box Rd - section 1

Indigo Valley

Indigo Creek Rd

2000

Watch Box Rd - section 2

Indigo Valley

Indigo Creek Rd

1400

Baxter Wheelan Rd

Barnawatha

Bay Rd

800

Marengo Rd

Chiltern Valley

Best Rd

900




11200


EAST




Road

Locality

Chainage Starts at

Length (m)

Fighting Gully Rd

Beechworth

Buckland Gap Rd

700

Pund Rd

Beechworth

Buckland Gap Rd

650

132 Buckland Gap Svc Rd

Beechworth

Buckland Gap Rd

150

Old Stanley Rd

Beechworth

Stanley Rd

600

Lower Nine Mile Rd

Stanley

Mt. Stanley Rd

350

Old Chiltern Rd

Beechworth

Beech-Wodonga Rd

500

Woolshed Rd

Beechworth

Beech-Chiltern Rd

2300

Factory Ln

Wooragee

Beech-Wodonga Rd

600

Fanning Ln

Wooragee

Star Ln

1200

Hodgson Ln

Yackandandah

Yack - Wodonga Rd

300

Simpson Rd

Kergunyah

Kiewa Valley Highway

1600

Elgin Rd

Beechworth

Red Hill Rd

100




9050


What is happening and when?

Works will commence on Monday 18 November and will take about three weeks to complete. During this time there won't be any road closures, but there may be some minor disruptions to the usual traffic flow.


About this project

We're commencing our annual program to resheet a proportion of the unsealed gravel roads across the Shire.

Why is this project being undertaken?

We routinely maintain around 1000km of unsealed gravel roads across the Shire. The 2024/25 program will see works completed on a number of roads in the east and west of the Shire, totalling approximately 20km. The roads will be graded, roadside drains will be improved, and new gravel material will be laid and compacted to improve driving conditions.

How is it being funded?

These works are funded through our Capital Works Program.

Funding Contributor
Amount
Indigo Shire Council
$680,000
TOTAL:
$680,000


Roads included in the current program

WEST




Road

Locality

Chainage Starts at

Length (m)

Cofield Lane

Wahgunyah

St Leonards Rd

400

Boundary Rd

Norong

West of Fed Way

2300

Melvilles Rd

Cornishtown

Great Northern

3400

Watch Box Rd - section 1

Indigo Valley

Indigo Creek Rd

2000

Watch Box Rd - section 2

Indigo Valley

Indigo Creek Rd

1400

Baxter Wheelan Rd

Barnawatha

Bay Rd

800

Marengo Rd

Chiltern Valley

Best Rd

900




11200


EAST




Road

Locality

Chainage Starts at

Length (m)

Fighting Gully Rd

Beechworth

Buckland Gap Rd

700

Pund Rd

Beechworth

Buckland Gap Rd

650

132 Buckland Gap Svc Rd

Beechworth

Buckland Gap Rd

150

Old Stanley Rd

Beechworth

Stanley Rd

600

Lower Nine Mile Rd

Stanley

Mt. Stanley Rd

350

Old Chiltern Rd

Beechworth

Beech-Wodonga Rd

500

Woolshed Rd

Beechworth

Beech-Chiltern Rd

2300

Factory Ln

Wooragee

Beech-Wodonga Rd

600

Fanning Ln

Wooragee

Star Ln

1200

Hodgson Ln

Yackandandah

Yack - Wodonga Rd

300

Simpson Rd

Kergunyah

Kiewa Valley Highway

1600

Elgin Rd

Beechworth

Red Hill Rd

100




9050


What is happening and when?

Works will commence on Monday 18 November and will take about three weeks to complete. During this time there won't be any road closures, but there may be some minor disruptions to the usual traffic flow.


Page published: 15 Nov 2024, 02:19 PM